We Have Three Phase! (April 10, 2009)
AEC, EDF and British Gas have done their respective bits and we have the required electricity supply! It's been a long time coming...
Haas Super Mini Mill delivery is booked for Tuesday 14th April and installation for Thursday 16th April.
Just the collection of a Colchester Lathe on Saturday 18th April and we have a go live start date of Monday 27th April.
Nearly there... Click here to return to the News page
|